Main building:

  • retaining wall erected
  • excavation pit constructed
  • the laying of the crushed stone base under the foundation slab has been completed.

Residences:

  • In 4 residences, the crushed stone and concrete base with waterproofing and thermal insulation have already been constructed, which is an important stage before pouring the slab.
  • External walls have already been erected in 8 more residences.
  • In 13 residences, roof parapets have been installed, and the areas have been prepared for laying the waterproofing layer.
  • External finishing works have been carried out in 3 residences, which indicates that the final stage is approaching.
  • In the observation residence, the replacement of the internal design.

Infrastructure and landscape:

  • The main internal road has been cut and formed.
  • A recreation area has been cut and formed along the internal road.
  • Landscape work has been carried out around the presentation residence: a slope has been formed with turf and a staircase has been erected.
  • The work is being carried out according to the schedule, covering all key stages – from the foundation and walls to landscaping and preparation for internal work.