Main building:
- retaining wall erected
- excavation pit constructed
- the laying of the crushed stone base under the foundation slab has been completed.
Residences:
- In 4 residences, the crushed stone and concrete base with waterproofing and thermal insulation have already been constructed, which is an important stage before pouring the slab.
- External walls have already been erected in 8 more residences.
- In 13 residences, roof parapets have been installed, and the areas have been prepared for laying the waterproofing layer.
- External finishing works have been carried out in 3 residences, which indicates that the final stage is approaching.
- In the observation residence, the replacement of the internal design.
Infrastructure and landscape:
- The main internal road has been cut and formed.
- A recreation area has been cut and formed along the internal road.
- Landscape work has been carried out around the presentation residence: a slope has been formed with turf and a staircase has been erected.
- The work is being carried out according to the schedule, covering all key stages – from the foundation and walls to landscaping and preparation for internal work.